Preparing for non-lead validation under the LCRI should start now

Every water system will need to validate their non-lead service lines or obtain a waiver under the LCRI. Here's why the time to plan your validation study is right now.

Most water systems face a 2034 deadline to validate their non-lead service line classifications under the Lead and Copper Rule Improvements (LCRI), but the planning starts now. For systems pursuing a waiver, the submission deadline is November 1, 2027, and all justifying work must be complete by then. Either path of a validation study or waiver takes more time, resources and coordination than most systems anticipate.

Validating non-lead service lines: Q&A

Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

If the deadline is 2034, why plan for validation now?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

What utilities underestimate is that this affects inventory accuracy, documentation, procurement, field logistics and multi-year budgets, too. For utilities operating on five-year capital plans or longer, early planning can keep costs more predictable and utilities can have a little more schedule flexibility.
Person in checkered blazer stands in a green park.

Davida Judelson

Procurement alone can take about 3–6 months. If locations are scattered, production may average 4 locations per day, per crew, or less. At that pace, plan on roughly 3–4 months of field work for one crew depending on total locations and access constraints. And build in about 3 more months to review results and compile documentation before submittal.
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

Build a schedule backward from deadlines. Procurement, field production and reporting can easily span most of a year.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

What are the paths utilities can take? Waiver, validation study or inspecting everything?
Person in checkered blazer stands in a green park.

Davida Judelson

There isn’t one “right” approach, and most utilities weigh three paths. The first is pursuing a waiver if their state permits. The second is running a validation study. The third is to physically inspect all service lines. In the third case, a utility would submit a validation pool of zero eligible service lines. The choice between a waiver, a validation study and a full inspection has real operational consequences. There are different costs, different timelines, different staffing and a very different story you'll have to tell regulators down the line.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

If a utility is pursuing a waiver, what do they need to submit by November 1, 2027?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

By November 1, 2027, utilities must submit their waiver request along with supporting documentation showing their completed study. State approval is not required by this deadline, but the study itself must be finished and the documentation ready to submit. It's important to note that the November 1, 2027 inventory is the first one eligible for use in an official study. This means utilities cannot begin their study using an earlier inventory and continue past the deadline. The study must be completed entirely before November 1, 2027, or use the November 1, 2027 inventory as the starting point going forward.
Person in checkered blazer stands in a green park.

Davida Judelson

For systems using the November 1, 2027 inventory, they may select their validation study properties from the available pool at that time and then have 7 years to investigate those sites. To help manage costs, some sites may be inspected in conjunction with other scheduled work.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

What documentation gaps make validation harder later?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

A physical inspection, a record of a physical inspection and a historical record carry different weight. Collapsing them into one bucket makes establishing the validation pool significantly harder. Separate “inspection” from “record” now so your inventory remains defensible and your validation pool stays as small as possible.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

Can historic records reduce the validation workload?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

If they’re properly documented, and clearly a record of a visual inspection, they can remove service lines from the validation pool completely.
Person in checkered blazer stands in a green park.

Davida Judelson

This matters because every service line removed from the pool could reduce the number of required validation inspections. For smaller systems, even the more modest reductions can make a significant difference on the scope and cost.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Hersbt

What happens if utilities find lead during validation study inspections?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

 When a line classified as non-lead turns out to be lead, the LCRI sets the required steps of the notification timelines and replacement for that service line. Utilities may consider reclassifying a group of service lines or changing material identification methods going forward so deciding the path early makes follow-through easier. However, ultimately the decision on follow-up lives at the state level. Additional federal guidance is not anticipated anytime soon.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

How much of validation depends on your state’s expectations?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

Validation is heavily state-driven. EPA sets the framework, but states review approaches, approve waivers, and decide what happens when results raise concerns. States decide whether certain records qualify as inspections, how modeling and statistical methods are accepted and what additional steps are required if validation results raise concerns. This makes early coordination with primacy agencies essential!
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

What does validation cost and how will small systems be impacted?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

Validation takes real resources, field work, data analysis, reporting, and follow-up, so it’s difficult to fund at the last minute. It’s important to build it into multi-year budgeting cycles.
Person in checkered blazer stands in a green park.

Davida Judelson

Potholing typically runs about $500–$1,500 per location and is used often when meter inspections aren’t feasible. In some areas, plan for $1,500+ per location. Water systems can assume spending several hundred thousand dollars to complete this study. Small systems with less than 1,500 services lines have to inspect 20% of the validation pool and will see a higher cost per service line in the pool. Large systems with more than 50,000 service lines will only need to inspect less than 1% of the validation pool, seeing a lower cost per service line in the pool.
Person wearing a red buttoned sweater indoors, with short brown hair and hoop earrings.

Rachel Herbst

What should utilities do now to keep validation defensible and cost-effective?
Person in a gray textured sweater poses outdoors with blurred plant background.

Joanna Cummings

Set yourself up for success by deciding which path makes the most sense for your system, cleaning up inventory classifications and pressure-testing inventory methods through a “will this end up in the validation pool?” lens.
Person in checkered blazer stands in a green park.

Davida Judelson

You also should determine what your state will expect and how approvals work. Build validation into long-range budgets and work plans, too. Non-lead validation will catch a lot of utilities off guard. Not because the deadline is unclear, but because the workload isn't obvious until you're already behind on scope, schedule and cost.

This framework is designed to assist water systems completing the EPA's LCRI validation study. Get support on how to conduct the study, evaluate the study results, and report the results to your State.

More resources on this topic

Child's hand near a water fountain with water flowing, indoors.
Insight

School and child care sampling: LCRI requirements

What do water systems need to know about lead testing in schools and child care facilities under the LCRI? We asked environmental health expert Davida Judelson, MPH, to break it down.
A woman working at a desk with dual monitors displaying charts and diagrams in an office environment.
Insight

Find lead faster: shrinking LCRI replacement lists with data-driven tactics

Katie Deheer, data science expert at Trinnex, explains how data-driven strategies help utilities reduce uncertainty and plan more realistic, defensible replacements to comply with the LCRI.
Construction worker in safety vest and hard hat shows a woman information on a tablet outside a house.
Insight

How to talk about lead programs with the public

As part of the Lead and Copper Rule Improvements (LCRI), water utilities are required to communicate with residents and businesses more than ever before about lead in drinking water. We’ve compiled four best practices to effectively communicate with customers.
Glowing digital envelopes on a dark background, symbolizing email communication.

Sign up for Lead and Copper Rule updates and more

Sign up for our newsletter to stay in the know on regulations, recent projects and the latest innovations to tackle lead in drinking water.