Skip to Main Content
CDM Smith logo
CDM Smith logo
Project background not configured

Practices

Water ResourcesRemediationConstruction SupervisionGeotechnicsTunnelling

Markets

Public Sector

New Construction of a Cutting‑edge Research Center

The new international accelerator facility, FAIR, is under construction in Darmstadt – one of the largest research building projects worldwide with an investment of € 1.2 billion. The facility aims to investigate previously unexplored states of matter, with experiments providing new information on the evolution of the universe around 13.8 billion years ago.

FAIR: World‑Class Research

The international large‑scale project sets extreme requirements for precision, stability, and radiation protection.

Combined Pile‑Raft Foundation

A sophisticated foundation system with FEM analyses and pile load tests ensures maximum stability under extreme loads.

Subsurface Testing at 60 m Depth

Extensive pile load tests and trial embankments increased planning and cost certainty.

Massive Earthworks

880,000 m³ of soil were excavated, temporarily stored, and later reinstalled.

The project involves building eight ring accel­er­a­tors with a circum­fer­ence of approx­i­mately 1,100 m, two linear accel­er­a­tors and 3.5 km of beam tubes at depths down to 17 m, all covering an area of around 20 hectares, with an embankment of up to 15 m height acting as a radiation shield to cover the equipment.

We have been commis­sioned with all of the geot­ech­ni­cal consulting and planning services as well as on-site construc­tion supervision for the project. Combined pile-raft foundations have been planned for all of the buildings except the accelerator ring. We used 3D finite-element calcu­la­tions to investigate the load-bearing and deformation properties of the subsoil under future load conditions, with a load test on a bored pile at 60 m depth and test filling to improve planning and costs. This resulted in 1,350 piles at a depth of up to 62 m and 60,000 m in length completed within just 14 months – exceptional performance given the location of the construc­tion site in a water reserve and the various require­ments applicable to the site.

“The sensitive state-of-the-art technology at FAIR places heavy demands on foundation design and subsidence analysis.” – Wolfgang Kissel, Senior Project Manager

The previous construction stage involved the early preparation of a deep excavation down to around 19 m below ground, which required partly lowering the groundwater for protection. Secant pile walling with beam supports was used to shore up the excavation area. The excavation pit covered around 57,000 m² of construction area in this section, and approximately 880,000 m³ of soil was excavated for intermediate storage in separate storage areas before being used for backfilling after shell construction.

Currently, the shell construction work is being completed in two of the three construction areas. The installation of underground pipework on a large scale is still pending so is the finalisation of the terrain modeling by reinstalling the excavated soil. The backfill around the research buildings will be raised to a height of around 14 metres above the original ground level. CDM Smith is currently carrying out quality monitoring as part of this process. Parallel to the exterior work, the technical interior work with the research facilities is also progressing.

 

Our services within this project:

  • Combined pile-raft foundation
  • Construction supervision
  • Contaminated site investigation
  • Excavation pit construction
  • Geotechnical investigation
  • Pile load testing

Visual Insights of the Project

Project Contact 

Have questions about the project or our services? Our expert is happy to help.

Wolfgang Kissel

Wolfgang Kissel

Senior Project Manager

The Senior Project Manager in Infrastructure and Geotechnical Engineering specializes in soil studies and foundation consulting.

Practices

Water ResourcesRemediationConstruction SupervisionGeotechnicsTunnelling

Markets

Public Sector

Project Figures

1,350 

number of bored piles

1.1 

km cir­cum­fer­ence ring ac­cel­er­a­tor

Related Projects

Explore our projects and the experts behind them!

View All Projects
Train passing under a bridge with construction equipment and gravel in the foreground.
Frankfurt, Germany

Connecting the Rhine-Main Region – Regionaltangente West

View Project
An industrial worksite with pipes, trenches, and building structures under a clear sky.
Bavaria, Germany

AUGUSTA Gas Transmission Pipeline

View Project
Overhead view of a highway, construction site, and snowy landscape.
Leipzig

A72 – Closing the Final Gap

View Project
CDM Smith logo

Let’s Build Something Together

Have a project in mind or want to stay in the loop? Reach out to our team or subscribe to get the latest updates from our work.
Contact Us

Europe Headquarters

CDM Smith SE
Am Umweltpark 3-5
44793 Bochum, Germany
What We Do
  • Markets
  • Practices
  • Priorities
  • Projects
Who We Are
  • About Us
  • Career
  • Find Us
  • News
Resources
  • Resources
  • Legal & Terms of Use
  • Privacy Statement
  • Imprint
CDM Smith™ | CDM™ | WILBUR SMITH™
© 2026 CDM Smith. All rights reserved.