The Babcock & Wilcox Company (B&W) has selected CDM Smith to complete the first phase of construction on the NG2H Massillon BrightLoop project. This first-of-its-kind hydrogen production facility will use new proprietary technology. Drawing on nearly 30 years of Balance of Plant (BOP) engineering services for B&W, CDM Smith’s Perry Group Limited (PGL) will be carrying out this project.
CDM Smith has provided approximately $5 million in engineering services since August 2023 for project development and BOP engineering. The team developed an Opinion of Probable Construction Cost (OPCC) for the BOP scope items in the summer of 2024 to support the client’s budget development and project funding requirements. The engineering team is finalizing IFC drawings based on vendor equipment information provided by the client and our construction team has mobilized to begin construction activities for the BOP scope items: Civil; Electrical; Foundations; Pre-Engineered Metal Building (PEMB); Building Mechanical (HVAC/Plumbing) and Construction Management services.
Pilot testing will be conducted and used to collect data and refine the process at the hydrogen production facility. The new facility will also support prospective data center clients’ energy and power demand. Construction is scheduled for completion in the spring of 2028.
“Our team collaborated alongside B&W, working closely with the client to develop the engineering design for the construction of the new facility. Drawing upon our engineering and construction experience, we were able to remain flexible throughout to meet the client’s criteria and project schedule to implement this new proprietary technology and energy solution."
Jim Calderone, client service leader.